6.02.22 - Power was turned on today, allowing the remaining trades to finish their work,
3.03.22 - Interior build out continues. Windows are installed,
2.08.22 - The building is sheeted. Erectors are installing the ridge vents. Framers have completed framing the office walls.
12.22.21 - The foundation was poured today,
7/01/21 - This new 8,600 SF office and warehouse is in permitting. Construction updates will be available on this page, so check back for this location's progress and availablility.
By accepting you will be accessing a service provided by a third-party external to https://northwindscomm.com/