12.15.19 - This property Available for Sale or Lease. Call for more information, 713-671-5300.
12.03.19 - Below are photos of the final interior,
10.05.19 - Landscaping is complete and flooring is near completion,
9.27.19 - Power has been set on the building. Landscaping is being installed. Next week the ceiling tiles and flooring will be installed,
9.13.19 - Flooring and landscape installation are underway,
8.09.19 - Electricians continue to run lights in the warehouse, while plumbers work on the waterline. Painting is underway. M&M Erectors finished trimming out the building,
7.11.19 - Masons are laying the stone. Interior crews are framing the walls. Septic tanks are being installed,
6.28.19 - This office/warehouse is now fully sheeted. Interior framing is underway, as additional crewmen frame for the next paving pours, and the erectors trim the facility,
6.06.19 - Erectors have progressed to installing the wall and skylight sheeting,
3.25.19 - Crews poured the front paving last week,
3.20.19 - Driveway is poured and the pad is complete. Concrete crews will be pouring the front half of the paving tomorrow,
12.09.19 - This project was completed in November and SiteOne is moving in,
10.14.19 - Interior painting is underway and landscaping installation will soon follow,
9.27.19 - Painters are wrapping up. Site crew is cleaning up the site. The building should have power next week,
9.09.19 - Crews are tying steel in preparation for Wednesday's paving pour,
8.19.19 - The building is fully sheeted and trimmed. Downspouts are installed and the side canopy. Interior framing is underway,
8.09.19 - M&M Erectors continue to sheet the roof. Site crewmen are grading for paving,
7.23.19 - Crewmen are erecting the building,
7.10.19 - Crews are tying steel for tomorrow morning's pour,
6.28.19 - Sitework continues,
6.26.19 - Crews broke ground on this project last week. It will be a new 7,000 SF retail center and showroom for a wholesale landscape and irrigation supplier SiteOne. Trevor Robinson is the PM.
10.15.19 - This project is complete for now. The office area will later be completed per tenant's request,
9.05.19 - This project is near completion. Tilt installation is underway then punch-out items will be addressed,
9.03.19 - Crews are painting the breakroom, restrooms, and doors. Lights were installed in the restrooms. M&M Erectors separated hanger doors 3 & 4, then repaired the weatherstrip after the separation,
8.16.19 - Electricians are working on the rolling hangar doors to prep for power. Flooring contractors began work by demoing existing tile in the women's room and by installing wall tiles in the men's room,
6.03.19 - Electricians are running extra grounding and cad welding to the columns,
4.29.19 - Electricians are installing exterior wall lights on the North side of the hangar. Crews continue to paint steel and conduit in the hangar areas. Crewmen are also breaking up the driveway, while A/C work continues in the offices, and blades are being installed on the big fan,
4.24.19 - The doors are complete. Electrical and interior painting continues. This project is near completion,
4.01.19 - Crewmen continue to trim and sheet the rolling doors, and line the interior hanger walls. Electrical continues as well as interior painting,
3.29.19 - Liner panels are being installed,
3.17.19 - Crewmen poured the door railings and continue to sheet the high roof with insulated roof sheeting. Crewmen are also installing the gutters and downspouts o the west side. Electricians continue hangers and conduit for the high bay lights as interior hangar walls are bing insulated and the gas line is being run in the hangar,
3.11.19 - Crewmen have progressed to sheeting the highest roof and installing the gutters and downspouts. Electrical work continues,
2.20.19 - Crewmen continue to sheet the lower roof. Electricians are roughing in the electrical and interior duct work is also underway,
1.21.19 - Crewmen are installing insulaton straps. Plumbers continue to relocate plumbing lines and the interior build out continues,
1.07.19 - Hanging rafters,
12.18.18 - Crews began hanging steel last week,
12.03.18 - The foundation has been saw cut,
11.29.18 - The foundation was poured this week,
11.19.18 - Crewmen are tying double rebar mat for the foundation,
10.21.18 - Crewmen have drilled 27 of the 32 piers,
9.24.18 - Crews are building pad for the foundation,
9.07.18 - Site excavation continues,
8.15.18 - Work began for Wilson Air's new 28,000 SF hangar and office, which is to tie into the hangar we constructed in 2014. Crewmen began breaking up the outside perimeter of slab,
10.10.19 - Subway will open next weekend. Below are final photos of this project. Final photos of Joe's Burgers are below Subway. Joe's Burgers will open this weekend,
Joe's Burgers,
10.02.19 - A final clean is underway for Subway,
10.01.19 - Joe's Burgers is complete,
9.24.19 - Joe's Burgers will be complete after the fire inspection and crewmen will wrap up their work on Subway at the end of the week,
8.21.19 - Crews began installing the stainless steel countertops and pass through window at Joe's Burgers,
Subway - Crews continue to install the metal facade and the vent hood,
8.20.19 - Electricians are building the service at Joe's Burgers. The galvanized pipe ceiling treatment is being hung and the kitchen equipment has arrived and is getting installed,
Subway - Metal facade is being installed. Electricians are hanging the pendant fixtures in the dining area. Kitchen wall tile installation is also underway.
8.09.19 - Crews are applying epoxy flooring in the kitchen area of Joe's Burgers, while M&M crewmen install the framing for canopies and the roof for the wash bay. Finishers are taping and floating at Subway. FRP is being installed in the kitchen. Electricians are running conduit,
7.29.19 - Paving and tile work are complete for Joe's Burgers,
7.08.19 - Masons continue to lay the brick as Carpenters install the ceiling treatments for Joe's Burgers. Roofers are installing curbs and electricians are roughing in the lights and switches at Subway.
Subway,
6.27.19 - Spiral ductwork is complete for Joe's Burgers. Vent-a-hood is installed. Masons started the brickwork.
6.25.19 - Window frames are installed and the roof is complete for Joe's Burgers. Electricians are roughing in the electrical, while HVAC contractors hang the spiral ductwork. --The block and water proofing is complete for Subway. Curbs are set and roofers began installing the iso board,
6.07.19 - Crewmen are installing hat channels for Joe's Burgers, and hanging steel for Subway,
6.03.19 - Crews have been addressing the CMU installation, setting embedded plates for the bar joists, and filling walls with concrete. As for Joe's Burgers, crewmen are laying out the roof curbs for the AC and vents, cutting AC access and welding angle supports, framing, and pouring interior curbs. Electrical rough-in is also underway.
5.29.19 - Crewmen began CMU installation for the Subway restaurant, which will be completed by the end of this week. We expect steel for this building to be delivered on 5/31, and will begin erecting.
Steel erecting is complete and inspected for Joe's Burgers. The roof deck is on and framing has begun. Crewmen plan to pour interior curbs and block outs this week, so framing and plywood can be completed.
5.06.19 - Erectors began hanging steel and the masons continue to build the CMU walls,
4.29.19 - . Joes slab was poured last week. Cmu install is scheduled to start today. As for Subway, crewmen were able to pour beams and prep for the slab pour. Subway's slab pour is scheduled for today and tomorrow.
4.03.19 - Underground is complete. Crews are digging beams and tying steel in preparation for next week's concrete pour,
3.25.19 - Crews are pouring piers today for Joe's Burgers. Plumbers ran the utilities for Subway and are backfilling today,
3.20.19 - The existing slabs are removed. Plumbers have made the utility connections and the boring for the fire main is complete. Concrete crews began tying steel for the piers.
3.17.19 - Crewmen ran utilities and poured trench for Joe's Burgers, and finished removing the slab for Subway,
3.08.19 - Crewmen are saw cutting and breaking out existing slabs, making tie-ins for water, sewer, and gas.
Parking lot expansion is complete,
12.21.18 - Fire inspection is underway,
12.20.18 - Final clean is complete. MUD District inspection is tomorrow, and the final fire inspection is Friday,
12.14.18 - This project is nearing completion. A final clean is scheduled for next week,
11.01.18 - Lights on and painters are applying final coat of paint,
10.30.18 - Lighting is complete. Crewmen are finishing the second coat of paint in the sanctuary,
9.12.18 - Crewmen are sheetrocking walls while Electricians rough in lighting,
8.13.18 - Electricians are roughing in the electrical, Mechanical contractors are installing ductwork, Finishers are taping and floating sheetrock, and M&M crewmen are installing the soffit and trim,
7.20.18 - Masonry and roof sheeting are underway. Crewmen are also framing the interior walls. Flatwork is 80% complete,
7.11.18 - Wall sheeting continues,
7.03.18 - Crewmen are forming up for aditional paving and installing additional purlins. Sheeting continues,
6.28.18 - Crewmen are pouring the first phase of paving this morning,
6.25.18 - Crewmen are forming up paving. Wall sheeting has begun,
6.18.18 - Progress erecting the church building,
6.13.18 - The building and detention lift station arrived,
6.11.18 - Flat work will begin in next few days,
5.30.18 - The foundation pour is underway this morning,
5.23.18 - Storm pipe installation, foundation ground out and forms,
5.11.18 - Crewmen are drilling and pouring foundation piers today,
4.25.18 - The big pond is 75% complete and the pad is 3" above final grade. Waiting on final compaction test today.
4.02.18 - Crews began excavating the detention ponds and continue to dewater the site,
3.23.18 - The site has been stripped of parking area,
5.20.17 - Today we celebrated at a ground-breaking ceremony for the Word of God Church. Construction will soon begin for their new place of worship.
This facility was purchased by Stillo Construction.
11.01.18 - The building is complete. Parking lot cleaning and striping to follow,
9.12.18 - Masons are installing the cast stone. Grid for the acoustical ceiling is being installed,
8.30.18 - Masonry work is underway as crewmen address HVAC and interior framing,
7.20.18 - Crewmen are installing exterior sheathing and are framing interior walls,
7.16.18 - Crewmen have progressed to roof sheeting,
7.06.18 - Crewmen continue to sheet the walls,
7.03.18 - All steel is hung and crewmen have progressed to sheeting the building,
6.25.18 - Crewmen began hanging steel,
5.01.18 - Paving is poured and sawcut. Crewmen begin seeding the detention pond,
4.26.18 - Crewmen poured the paving this morning,
4.12.18 - Crewmen are setting the storm for Spec Bldg 1. Electricians are trimming out electrical service panel for pond lift station and water well,
3.28.18 - Crewmen poured the foundation this morning,
3.23.18 - Excavation of the detention pond is complete. Slab is made up and ready to pour,
3.13.18 - Progress on the water tank and the detention pond,
1.09.18 - The pad is built for this new facility and crewmen are grading the detention pond. This new office/warehouse is Available for Sale or Lease, off Clay Rd in Katy,
This project is complete,
5.04.18 - Waiting on fire marshall approval and final clean.
4.02.18 - Waiting on fire marshal approval.
3.23.18 - Landscaping is underway. The building is complete. Addressing punch out items, cleaning up site, and waiting for power,
1.25.18 - Pouring retaining walls,
1.08.18 - Crewmen are currently taping and floating,
12.13.17 - Crews poured paving this morning,
10.30.17 - Building is sheeted and interior framing underway,
10.25.17 - Sheeting continues,
10.15.17 - Crewmen are hanging steel,
10.06.17 - Pouring the foundation,
9.15.17 - Pad progress,
7.31.17 - Working on the pond and site grading,
6.28.17 - Site work began mid-June.
5.31.17 - Sitework will soon begin for the first of 10 buildings in a new business park off Clay Road in Katy. This first building will be 12,374 SF (Total) with a 2,708 SF office and 9,666 SF Warehouse.