O'Neills Inflight Catering | 10,000 SF Interior Demo and Remodeling | Houston, TX
8.23.24 - Fire inspections are underway. The epoxy flooring is complete,




8.19.24 - Kitchen equipment installation and electrical trim out work continues,






8.13.24 - Kitchen work continues. The warehouse is clean and epoxy flooring will follow.










8.09.24 - Sign installation is underway. The kitchen is nearing completion,



8.07.24 - Kitchen equipment installation continues,

8.06.24 - Electrical work continues, flooring is nearing completion, the exterior canopy is installed,




7.30.24 - Parking curbs are installed, flooring continues, and restroom partition installation is nearing completion,





7.26.24 - Flooring continues,


7.22.24 -





7.17.24 - Painting continues,



7.16.24 -



7.12.24 - Lights are on,



7.10.24 -



7.02.24- Inspections are complete and requirements are met, so ceiling tile installation and final clean will follow,


6.28.24 - Kitchen equipment arrived, restroom partitions are in place, and the final painting is complete,





6.17.24 - Tile installation is underway,

6.10.24 - Exterior trim is complete. Ceiling grid installation is complete. Electricians trim out the interior,


5.08.24 - Crews are taping, floating, and sanding interior walls,



4.26.24 - Plumbers are roughing in the plumbing as additional crews begin sheetrocking the interior walls,



3.01.24 - Warehouse steel painting is complete. Crews are currently installing the insulated metal wall panels,

2.01.24 - Interior buildout demolition continues,



12.04.23 - MEP interior demolition is underway,


This project includes the renovating of an existing 10,000 SF warehouse for commercial kithcen use.